Riverside (Briscoe) in conjunction with the Town of Ajax has retained Hard-Co Construction Limited to complete the following work from Delaney Drive to Rossland Road.

  • Adjust catch basin and maintenance holes frames and covers.
  • Complete fine grading work at the Trail Head parking lot.
  • Complete top asphalt paving on Riverside Drive and the Trail Head Parking lot.
  • Complete the installation of new fencing on Toronto Regional Conservation Authority property.
  • Complete pavement marking and signage.

The work is scheduled to start in the week of May 31, 2019, and be completed by the week of June 14, 2019; weather dependent.

Vehicle and pedestrian access will be maintained to all local residents and the Golf Course on Riverside Drive during construction. In the event that a lane restriction is required to do the work, flagging operations will be in place to ensure the safety of motorists and pedestrians. 

Please ensure that all fixtures and equipment such as irrigation systems within the public right-of-way are removed prior to the start of the road excavation. The Town will not be responsible to repair the damage of existing lawn sprinkler/ irrigation systems or other fixtures or equipment installed by residents within the public right-of-way (the area beyond your property line).

The Town of Ajax realizes that the construction work will be disruptive to you. We sincerely appreciate your understanding and patience in this regard and we will make every effort to complete the construction work as quickly and efficiently as possible. 

If you have any questions or would like any further information, please go to our website or contact one of our team members.

Contacts

Town of Ajax              
Attention: Ranil Fernando,
Infrastructure and Asset Management Engineer
Phone: 905-619-2529 ext. 4241
Email: ranil.fernando@ajax.ca

Chisholm, Fleming and Associates
Attention: Robert Friscioni
Construction Services / Administration Manager
Phone:416-779-5667
Email: Robert.Friscioni@chisholmfleming.com